What a chip fab costs, and where the money goes.

A leading-edge fab now runs to $20 billion or more, and most of it is spent on tools rather than the building. Here is the breakdown, with the real figures behind recent US projects.

  1. The short answer
  2. Where the money goes
  3. Lithography and nodes
  4. US projects and subsidies
  5. Running costs
  6. Mature and specialty fabs
  7. Common questions
8 min read 21 sources, linked below

Part 01

A leading-edge fab costs $20 billion or more.

The most widely quoted estimate comes from the analyst firm International Business Strategies (IBS). In late 2023 it put a 3 nm fab with about 50,000 wafer starts per month at around $20 billion, and a comparable 2 nm fab at around $28 billion.1 Those are estimates for a single high-volume module, not audited costs.

The headline figures in the news are larger because they describe campuses, not single fabs. TSMC's Arizona site was planned as more than $65 billion for three leading-edge fabs.2 In March 2025 TSMC said its total US investment was expected to reach $165 billion, adding three more fabs, two advanced packaging facilities and an R&D centre.3

Most of that money does not go into concrete. SemiAnalysis estimates that about 80% of the cost of a fab during its initial build-out is equipment.4 The building is the cheap part; the tools inside it are the expensive part.

3 nm fab, ~50k wafers/month (IBS, 2023)
~$20bn1
2 nm fab, ~50k wafers/month (IBS, 2023)
~$28bn1
Equipment share of initial build-out
~80%4
TSMC's planned total US investment (2025)
$165bn3

Part 02

Tools take most of the money; the building takes the rest.

A fab budget splits into two broad pools. One is the shell and facility: the cleanroom, the sub-fab beneath it, ultrapure-water plants, chemical and gas distribution, exhaust abatement and power. The other is wafer fab equipment: lithography scanners, deposition and etch chambers, implanters, furnaces, polishers and metrology tools.

Industry-wide spending shows the same split. SEMI projects that worldwide 300 mm fab equipment spending will reach $149 billion in 2026, while fab construction spending will rise to $47.5 billion in the same year.5 SEMI expects construction to climb further, to $63.3 billion in 2027 and $68.4 billion in 2028, as new sites break ground.5

The building is still a serious engineering project. Bosch's 300 mm fab in Dresden, which opened in June 2021, cost about €1 billion and has roughly 10,000 m² of cleanroom.6 Cleanroom space is built to control particles, vibration, temperature and humidity at a level ordinary industrial buildings never approach; the Academy lesson on the cleanroom explains why.

Equipment is also why fab costs arrive in stages. A shell can be built with space for future tools, and the tools are bought as demand appears. That is why companies announce a site figure, then spend it over many years.

Part 03

Lithography drives the cost up at every new node.

The single most expensive tool in a leading-edge fab is the EUV scanner. In February 2024 Tom's Hardware reported that ASML's existing low-NA EUV systems cost around €170 million ($183 million), depending on model and configuration.7 Reuters reported in June 2024 that the next-generation High-NA tool costs about €350 million ($380 million).8

Each new node uses more EUV exposures. SemiAnalysis counted roughly 25 EUV layers on TSMC's original N3 process, almost double the number on N5.4 More layers per wafer means more scanners to hold the same output, and every scanner brings its own share of track, etch, deposition and inspection tools. The Academy lesson on lithography covers why EUV exposures are so hard to replace.

IBS attributes most of the jump from a $20 billion 3 nm fab to a $28 billion 2 nm fab to the extra EUV tools needed to keep capacity at 50,000 wafer starts per month.1 The cost flows straight through to wafers: IBS estimated about $20,000 to process an N3 wafer and about $30,000 for an N2 wafer.1

Capacity is the other lever. A fab's price is roughly proportional to how many wafers it starts each month, because tool count scales with throughput. Two fabs at the same node can differ in cost by billions simply because one is sized for twice the output.

Part 04

Recent US projects, and what the government paid towards them.

The CHIPS and Science Act of 2022 gave the Department of Commerce $52.7 billion, of which $39 billion is for manufacturing incentives. It also created an investment tax credit expected to cover up to 25% of qualified capital spending.9 In July 2025 Congress passed an increase in that credit from 25% to 35%.10

Announced leading-edge and memory projects in the US. Figures are company or government headline numbers at the date given; see sources.
ProjectHeadline investmentWhat it coversCHIPS direct funding
TSMC, Phoenix AZ>$65bn (2024); $165bn total US plan (2025)23Three fabs from N4/N5 to N2 or beyond, then three more fabs, two packaging plants, R&D113Up to $6.6bn, plus up to $5bn in loans2
Intel, New Albany OH$28bn12Two leading-edge fabs for Intel 14A and later nodes13Up to $1.5bn13
Intel, Chandler AZPart of nearly $90bn of Intel US investment by the end of the decade14Two new fabs and one modernised, for Intel 18A15Up to $3.94bn15
Samsung, Taylor TXOver $37bn in the region16Two 2 nm logic fabs, an R&D fab, Austin expansion16Up to $4.745bn16
Micron, NY and ID~$100bn NY + $25bn ID over two decades17Memory fabs; about $50bn before the end of the decade17Up to $6.165bn17

Grants cover a minority of the bill. TSMC's $6.6 billion grant sits against more than $65 billion of investment in its first three Arizona fabs, and Commerce pays it out as TSMC completes project milestones.2 Samsung's final award was about $1.7 billion smaller than the preliminary figure of up to $6.4 billion announced in April 2024.18

Timelines move. As of March 2025, Intel expected to finish its first Ohio fab in 2030 and begin operations by the end of 2031, about half a decade later than first planned.12 In August 2025 the US government took a 9.9% stake in Intel for $8.9 billion, funded partly by $5.7 billion of CHIPS grants that had been awarded but not yet paid.19

Part 05

Running a fab consumes water, power and people at industrial scale.

The best public numbers for a single leading-edge site come from the US government's draft environmental assessment of TSMC Arizona, published in 2024. It estimates city water demand of 4.75 million gallons per day for the first phase and 17.29 million gallons per day across all three phases at full production.11

Electricity is the larger bill. The same document estimates 2.85 gigawatt-hours per day for each phase and 8.54 gigawatt-hours per day for all three combined, with renewable energy credits bought to cover purchased electricity.11 Scanners, abatement systems and the air handling that keeps the cleanroom clean all run around the clock.

Staffing is smaller than the building suggests but highly skilled. TSMC estimated about 1,150 direct employees for the first Arizona phase, and about 6,150 employees and vendors travelling to the site each day once all three phases were running.11 Bosch planned up to 700 associates for its Dresden fab.6

The largest running cost is usually invisible on a utility bill: depreciation. Tools bought for billions must be written off over a period of years, so a fab that runs below capacity, or at poor yield, loses money quickly. Materials, masks, spare parts and service contracts add to the total.

Part 06

Mature-node and specialty fabs cost a fraction as much.

Not every chip needs 3 nm. Bosch's €1 billion Dresden fab processes 300 mm wafers with structures down to 65 nm, making ASICs and power semiconductors.6 That is a small fraction of the IBS estimate for a 3 nm fab, though the two plants differ in capacity as well as node.

The European Semiconductor Manufacturing Company in Dresden, TSMC's joint venture with Bosch, Infineon and NXP, sits in between. Its total investment is expected to exceed €10 billion for a fab of 40,000 300 mm wafers a month on 28/22 nm planar and 16/12 nm FinFET processes.20

Older nodes need no EUV, fewer mask layers and fewer process steps, so each wafer needs less tool time. Many specialty processes still run on 200 mm wafers, where tools are smaller and long established. SEMI projected in 2022 that 200 mm capacity would exceed 7 million wafers a month by 2025, with automotive and power capacity growing 58% from 2021.21

The trade-off is what each fab can make. A mature-node line suits power, analogue, sensors and microcontrollers, but not frontier logic. Advanced packaging and test add further capital on top of either; the Academy lesson on advanced packaging covers that stage. The cost of standing up a line, and of choosing which capabilities it really needs, is the problem Synthesys is being built around.

Part 07

Common questions.

How much does it cost to build a semiconductor fab?

A leading-edge logic fab with about 50,000 wafer starts a month costs roughly $20 billion at 3 nm and $28 billion at 2 nm, according to 2023 IBS estimates.1 A mature-node 300 mm fab can cost far less: Bosch's 65 nm Dresden fab cost about €1 billion.6

Why are semiconductor fabs so expensive?

Mostly because of the equipment, which SemiAnalysis estimates is about 80% of a fab's initial build-out cost.4 Each new node needs more EUV exposures, and each EUV scanner costs hundreds of millions of dollars.

How much does an EUV machine cost?

Low-NA EUV scanners cost around €170 million ($183 million), depending on configuration, as reported in 2024.7 ASML's High-NA EUV tool costs about €350 million ($380 million).8

How much did the CHIPS Act give to chip fabs?

The act set aside $39 billion for manufacturing incentives.9 Large awards included up to $7.865 billion for Intel, $6.6 billion for TSMC Arizona, $6.165 billion for Micron and $4.745 billion for Samsung.1421716

Next

Keep reading.

Synthesys is building a manufacturing line for frontier compute: fabrication, advanced packaging and test on one line, with every wafer traced. If you are planning silicon and want to talk it through with an engineer, we would like to hear from you.

Talk to us

Sources

Where the figures come from.

  1. Tom's Hardware (reporting IBS estimates) “Firm predicts it will cost $28 billion to build a 2nm fab and $30,000 per wafer, a 50 percent increase in chipmaking costs as complexity rises” (2023-12-22). tomshardware.com
  2. NIST / U.S. Department of Commerce “Biden-Harris Administration Announces CHIPS Incentives Award with TSMC Arizona” (2024-11-15). nist.gov
  3. TSMC “TSMC Intends to Expand Its Investment in the United States to US$165 Billion to Power the Future of AI” (2025-03-04). pr.tsmc.com
  4. SemiAnalysis “TSMC's 3nm Conundrum, Does It Even Make Sense? N3 & N3E Process Technology & Cost Detailed” (2022-12-21). newsletter.semianalysis.com
  5. AnySilicon (reporting SEMI) “SEMI 3Q26 300mm Fab Outlook: global 300mm fab equipment spending to reach $227 billion in 2029” (2026-10-13). anysilicon.com
  6. Bosch “300 mm wafer fab in Dresden (factsheet)” (2022). bosch-presse.de
  7. Tom's Hardware “ASML's High-NA chipmaking tool will cost $380 million” (2024-02-13). tomshardware.com
  8. Reuters (via The Star) “ASML, Belgium's Imec open laboratory to test newest chip-making tool” (2024-06-03). thestar.com.my
  9. NIST / U.S. Department of Commerce “CHIPS for America Fact Sheet: Federal Programs Supporting the U.S. Semiconductor Supply Chain and Workforce” (2024-03-18). nist.gov
  10. Semiconductor Industry Association “SIA Applauds Passage of Strengthened Semiconductor Investment Credit” (2025-07-03). semiconductors.org
  11. NIST CHIPS Program Office “Draft Environmental Assessment for TSMC Arizona (NIST-CPO/EA-002)” (2024-05-29). nist.gov
  12. SDxCentral “Intel further delays $28bn Ohio chip fabs by half a decade” (2025-03-03). sdxcentral.com
  13. NIST CHIPS for America “Intel Corporation (Ohio) project page” (2024). nist.gov
  14. NIST / U.S. Department of Commerce “Biden-Harris Administration Announces CHIPS Incentives Award with Intel” (2024-11-26). nist.gov
  15. NIST CHIPS for America “Intel Corporation (Arizona) project page” (2024). nist.gov
  16. NIST CHIPS for America “Samsung Austin Semiconductor CHIPS award project page” (2024). nist.gov
  17. NIST / U.S. Department of Commerce “Department of Commerce Awards CHIPS Incentives to Micron for Idaho and New York Projects” (2024-12-10). nist.gov
  18. Reuters (via The Star) “US finalizes up to $6.35 billion in chips awards for Samsung Electronics, Texas Instruments” (2024-12-21). thestar.com.my
  19. Engadget “The US government is taking an $8.9 billion stake in Intel” (2025-08-22). engadget.com
  20. TSMC “ESMC Breaks Ground on Dresden Fab” (2024-08-20). pr.tsmc.com
  21. SEMI (via PR Newswire) “Global 200mm Semiconductor Fab Capacity Projected to Surge 20% to Record High by 2025, SEMI Reports” (2022-10-18). prnewswire.com